Just Get More People, Right?

Wrong.  Consider the following when you are behind in schedule or have a newly added chunk of work to your project: Phase the new work to after you finish the already planned project work Have you taught someone to drive, do dishes, play a board game?  It takes more than double the time to do

Seriously Morphed Requirements

Lost in translation can describe 2nd, 3rd, and 4th handed information that is passed on as “necessary” requirements, causing PM’s to plan in one direction while ending up in a completely different place 1/2 way through planning. On one project, between the first list of needs relayed and an onsite assessment, the equipment list was